Midagon Company logo
  • Services

    Services

    • ERP & Core System Transformation
    • Sales & Product Transformation
    • Supply Chain Transformation
    • Production & Operations Transformation
    • Finance Transformation
    • Mergers & Acquisitions
    • IT Transformation & Cyber Security
    • Banking & Insurance
    • Program Management & Agile Leadership
    • Sourcing & Vendor Management
    • Data & Analytics
    • Architecture

    Are you ready for transformation?

  • Cases
  • Insights

    Insights

    • Blog
    • White papers
    • Point of Views

    Are you ready for transformation?

  • About us

    About Us

    • About Us
    • Culture & values

    Are you ready for transformation?

  • Team
  • News
  • Careers
  • Contact us
  • Are you ready for transformation?

Back to cases

Valmet on-time delivery improvement task force

Improving customer experience with on-time delivery accuracy and purchase order automation

Key benefits

%

Improved on-time delivery accuracy

%

Purchase order automation level reached

The challenge

Valmet's logistics center in Hyvinkää had a low on-time delivery accuracy and the situation was impacting negatively on customer satisfaction. Corrective actions were needed to improve the situation.

How Midagon helped

Midagon's consultant established a task force with relevant parties, including ERP system development, procurement as well as Hyvinkää logistics and business line management. A root cause analysis was made to identify the main areas that needed to be improved. After this, corrective actions were initiated.

No single “silver bullet” was found but various corrective actions were chosen. These were related to the ERP system and master data, additional resourcing in key improvement areas, and finally, a quality audit execution in the logistics center to identify the main bottlenecks in the logistics center itself.

Results achieved

The areas that needed improvement were identified and corrective actions were started. Some of these were still ongoing at the end of the assignment. ERP development needs were documented and included into the normal ERP development process. ​​A volume forecasting process was established to provide visibility to the required warehousing capacity at the logistics center. ​Within 6 months time, on-time delivery improved by 25% and purchase order automation level by 214%.

Contact for more information

Nyman Jari Midagon

Jari Nyman

Senior Managing Consultant

+358 50 487 7566

jari.nyman@midagon.com

Related cases

  • Data-driven supply chain analysis

White Midagon footer logo

    About

  • About us
  • Meet the Team
  • See all Cases
  • Contact us

    Insights

  • Blog
  • White papers
  • Point of Views

© 2025 All rights reserved. Midagon Finland, 2058234-3

  • Privacy policy
  • Cookie policy

Accountor Tower, 19th Floor, Keilaniementie 1, 02150 Espoo, Finland